Pre-Shipment Inspection — Alpha Press Battery Hydraulic Crimping Tool Kits
Luckee conducted a full-quantity pre-shipment QC inspection of 174 Alpha Press crimping tool kits across 6 product lines at the Emeads facility in Yuhuan, Taizhou. One major defect was identified — a 108mm M-profile collar failing the crimping roundness requirement — triggering a Pending verdict and corrective action hold.
Inspection Outcome — AQL Critical 0.0 / Major 0.65 / Minor 1.5
Full quantity (174 units) inspected at General Inspection Level GII with Special S-1. Three defect classes assessed independently.
PENDING — Shipment on hold pending corrective action on major defect
8-Point Product Specification Assessment
Each criterion assessed independently with defect counts by class. All criteria were measurable and applicable.
| Inspection Requirement | Critical | Major | Minor | Status |
|---|---|---|---|---|
| B1 — Material should be certificated | 0 | 0 | 0 | Pass |
| B2 — All components correct and complete | 0 | 0 | 0 | Pass |
| B3 — Workmanship, finish and appearance | 0 | 0 | 3 | Minor ×3 |
| B4 — Dimensions within tolerance range | 0 | 0 | 0 | Pass |
| B5 — Labels match approved files | 0 | 0 | 0 | Pass |
| B6 — Function test: crimping pipes | 0 | 1 | 0 | Major ×1 |
| B7 — Product marking matches approved sample | 0 | 0 | 0 | Pass |
| B8 — Packaging safe and qualified | 0 | 0 | 0 | Pass |
3 Defects Documented — 1 Major, 2 Minor
Every defect was photographed and classified by type. The major defect triggers the shipment hold; minor defects are noted for corrective action on the next production run.
108mm STD M-Profile Collar — Oval Crimping Failure
Sharp Burrs on 15, 22 & 28mm Die Profiles (JT-1632)
PZ-2340 Case Cavity Incorrect — Two Remediation Options
4 MPa Water Pressure Test — No Leakage Found
Independent pressure testing was conducted on-site using the PZ-3240 battery press tool with 15mm and 35mm M-jaw dies. Press-fit copper fittings were crimped and pressurised to 4 MPa via manual hydraulic test pump.
✓ Leakage Test — Passed
All Photos Taken During the Inspection
Every photo was taken on 13 October during the on-site inspection. Click any image to enlarge.
Actions Before Shipment Can Proceed
Four items require resolution. The first is a hard blocker for shipment; the remaining three are required before the next production run or can be resolved in parallel.
HOLD — 108mm M-profile collar: root cause investigation and re-inspection required
PZ-2340 case: buyer to confirm EVA foam or plastic cavity solution
JT-1632 M-profile kit: 4 more production days required
ED-1550: 2 more production days required
Pending — Shipment Held Pending 108mm Collar Re-Inspection
The inspection identified one major functional failure (108mm M-profile collar — oval crimp) and three minor defects. Critical passed with zero findings. Pressure testing at 4 MPa confirmed zero leakage across all tested jaw sizes. Shipment is approved to proceed only after the 108mm collar defect is resolved, the JT-1632 and ED-1550 kits are completed, and a Luckee re-inspection confirms conformance.
Need a pre-shipment QC inspection?
We catch defects before they ship — not after your customer finds them. AQL-based inspection with full photo evidence and same-day reporting.
Explore: quality control service · AQL guide · inline valve inspection · steel plate QC.
Book a QC Inspection →